Renewal Project Update – Number 4 – 1 August 2016

In preparation for the Refurbishment work the Hall contents have been removed and are being installed in a fully insured storage unit. Many thanks to Alan & Jane Cronin, Dave & Val Francis, Mike & Sally Woodhouse, & Ian Fothingham  for devoting most of their weekend to the task.
The Village Hall construction team met with the School and agreed access and health and safety issues.
At a meeting with the building professionals on Friday 29th July the following was agreed:
  • I J Preece and Sons Ltd of Hereford were formally appointed as main contractors
  • Start date of the project is Monday 8th August 2016
  • Forecast end Date of the project is Friday 2nd June 2017
  • Total number of project weeks is 43 weeks including statutory holidays and two weeks holiday at Christmas and one weeks holiday at Easter
  • Working hours 7.35hrs to 17.00hrs – Monday to Friday